Hi,

In our ITSM we are using a custom status, and we would like to start the MPT calculation from status 4 (it currently starts at status "3 - in process", which is a defualt SAP status).

I however does not know how to set up and indicate to the system at which status the MPT or IRT has to start. Is it at the "setting for duration" activity?

thanks,

Dimitri

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Mar 10, 2017 at 12:23 PM

    Hi,

    Under: spro --> sap solution manager --> capabilities --> it service management --> sla escalation --> specify customer Time status

    Here you can specify which statuses that "stops" the MPT timer. For example you have as standard:

    Which indicates that for transaction SMIN, the following statuses stops the timer: E0003(Customer action), E0004(sent to SAP), E0005(proposed solution), E0008(closed), E0010 (withdrawn)

    Hope this helps!

    /Mike

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 13, 2017 at 07:53 AM

    Thanks, it helped :)