Skip to Content
0

SAP AFS QM

Mar 10, 2017 at 10:52 AM

72

avatar image

Hi Experts,

Can you please provide your advise on inspection set up for combined production order scenario in SAP AFS QM.

What is steps and procedure to do in process inspection and final inspection for combined production order scenario.

Thanks & Regards,

10 |10000 characters needed characters left characters exceeded

The question is really beyond the intent and purpose of the forum. You are asking for a lot of steps, and a lot of information. The forum is really not for that. We will help if we can but this is a pretty wide open question. Without know the actual business requirements, it would be almost impossible to provide an adequate answer.

What have you been able to do so far? Are you having a specific issue?

Craig
0

Thanks for your response.

My question is very simple and its applicable to any business in gloabally(Any manufacturing company).

Produciton order operation (I will combine more than one production order and will confirm operation using transaaction code J4A|)

10 - Forming

20- Winding

30 - Testing (inspection)

40 - Assembling

50 - Final confirmation

But i cannot do inspection for combined order through J4A|. Here my question is how i can do conbined inspections ?

Please advise .

Thanks

0

Well, it's really not applicable to any business. I don't even have the transaction you provided in my system, - J4A|

Any chance that is a typo?

I suspect that might be unique to the AFS solution?

Craig

0
* Please Login or Register to Answer, Follow or Comment.

0 Answers