Skip to Content
avatar image
Former Member

Reg SC convertion into PO in ECS scenario

Hi,

Why does the Shopping cart created in EB system with more around 19 line items show the status as Item in transfer process even though the entire approval workflow is complete?

There are no alerts found. Neither are there shortdumps.

The account assignment is of asset type.

The PO has not been created in the backend.

The function module to generate PO in the backend i.e. BBP_REQREQ_TRANSFER also does not convert the SC into PO.

Kindly guide as to what could be the reason for the same and the necessary corrective action required.

Thanks in Advance.

With Regards,

Rajesh

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Jul 20, 2006 at 12:49 PM

    Hi Rajesh,

    A basic doubt.

    In yr title you have said yrs is a ECS.

    In ECS the leading PO is to be made in EBP which is replicated in backend for ref and follow on docs.

    Are you expecting that after SC approval the PO should be created auto in backend ?

    In yr case it won't.

    For that you need

    classic scenario

    and customizing setting

    SRM IMG->SRM->SRM server ->cross applns->define objects in backend sys->PO if data complete

    No ranges and trans types properly maintained

    SC has a source assigned

    BR

    Dinesh

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 20, 2006 at 12:52 PM

    Hi

    Is this PO a service PO, with all line items being services..?

    Have you checked in BBP_PD and RZ20...!!

    Similar problem we faced, if the PO has more than 19 service items or limit items, it goes into error in process...

    Regards

    Reddy

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Reddy,

      Ya I checked in BBP_PD & RZ20 but there are no alerts in this case.

      With Regards,

      Rajesh

  • avatar image
    Former Member
    Aug 02, 2006 at 10:05 AM

    I would like to provide the solution for this case which was the line items should be itemized in case of an asset assignment.

    Add comment
    10|10000 characters needed characters exceeded