0 Kudos

What are the settings required for quota arrangement?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

<b>Quota Arrangements</b>

<b>Use</b>

If a material can be obtained from various sources of supply, each individual source of supply can be allocated a quota arrangement. The quota arrangement is valid for a certain period of time and specifies exactly how the receipts are to be distributed amongst each source of supply.

You can set the quota arrangement for in-house production as well as for external procurement. Sources of supply can be:

an individual vendor or outline agreement

another plant, from which material should be procured

a production version

<b>Prerequisites</b>

You have maintained the quota arrangement usage for the respective material in the material master (MRP 2 view).

The quota arrangement usage determines whether a material is included in a quota arrangement and which operations lead to a quota arrangement. You can define, for example, that only purchase orders are included in quota arrangements or that procurement proposals created by the system in the planning run are also included.

You define the quota arrangement usage in Customizing for Purchasing in the IMG activity Define quota arrangement usage.

You have maintained the quota file for the material.

You define the sequence of the sources of supply, the quotas per source of supply and numerous other parameters in the quota file.

<b>Features</b>

During the planning run, the system determines the sources of supply according to the quota file and assigns the procurement proposals to the sources of supply.

In external procurement, the procurement proposal is allocated to the appropriate vendor. This vendor is copied to the purchase requisition.

For every procurement proposal with a quota arrangement, the system updates the quota file, so that the quota arrangement is always based on the current situation.

Two procedures are available:

Allocation quota arrangement: every lot is assigned to a source of supply

Splitting quota arrangement: a lot is split among various sources of supply

Further functions are also available for controlling quota arrangements. For example, you can set a maximum release order quantity that defines the maximum delivery capacity of one particular vendor.

Activity

Transaction

Maintain quota arrangement

MEQ1

Display quota arrangement

MEQ3

Display changes to quota arrangement

MEQ4

Analyze quota arrangement

MEQ6

Delete quota arrangement

MEQ7

Monitor quota arrangement

MEQ8

Quota arrangements per material

MEQM

Go thru this link, which will be useful.

http://help.sap.com/saphelp_47x200/helpdata/en/75/ee115f55c811d189900000e8322d00/frameset.htm

Hope this helps.

Thanks,

Viswanath

Former Member
0 Kudos

Hi,

I just would like to ask you,please:

If you manually create Quota Arrangement for a Material and it should be procured at 100% from one Plant even if trasportation lanes exist also for others Patner Locations, is it necessary to consider all the locations putting Quota Arrangement 0% for the ones not used and the 100% for the only one considered or not?

Which Consequences?

Thanks in advance

Elisa Basso

Answers (0)