Hi SAP gurus,

I am new to this amazing forums.What is the best possible way to configure Post dated Check, both in case when client gets Check discounted or otherwise??

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

As far as I know, there is no direct functionality to address the issue of post dated checks.

Nevertheless, you can either:

1. Use special GL indicator, as suggested by Ravi.

or

2. Use t.code FBW5 (AR) or FBW6 (AP).

Cheers...

Answers (1)

Answers (1)

former_member197269
Active Contributor
0 Kudos

Hi Anand,

Welcome to SDN !!!

Try using special G/L and use manual check for post dated check.