After making an an MRP run for single material in MD02 the planned order is not generated when i see in MD04. Can anyone explain any prerequisite to be done or what procedure to be carried out.

Regards,

Vajravel S

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Solomon Macwan Mar 08, 2017 at 08:32 AM
0

Hi Vajravel,

Please search the net before you post a question

hope this helps.- https://blogs.sap.com/2015/11/16/what-can-i-do-if-mrp-does-not-plan-a-material/