With MRP or Without MRP

Dear Experts,

Here is one of clients requirement,

Our client will be entering POs in the system on 15th of every month. the system has to send the required quantities to the Demand Planning team for the production planning.

Our client wants the system to send regular reminders to the DP team for the release, movement of the stock to the desired locations and the timely delivery to the customer.

Apart from this, the customer will also provide RSF for the next 3 month to help us plan the RM/ PM.

Kindly note that there is no MRP run in the present system.

In material master the MRP type is ND and no strategy group.

The industry is the process industry.

We strongly feel that MRP should be implemented in system with Strategy group as 40

Kindly provide you valuable inputs on how to implement the above scenario in sap

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Mar 08, 2017 at 09:42 AM

    Hi Chinna,

    Your requirement is bit confusing. Let me say this way -

    When the sales team recives the po they create the sales order, based on that the planning team can run the MRP and get the planned orders or production order. Based on the Plan or Production order shop floor people can do the production.

    Now as far as reminders are concern it is a part of workflow. Althogh if you create a plan or production order, you can easily see all these things like when the order was released, how much qty delivered, delivery date and so on.

    let me know if you need any more help

    regards,

    Solomon

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Solomon,

      Thank you for your swift response

      Since there is no MRP run and no availability check at process order level and sales order level in the current system, is it suggestible to implement MRP in the existing system?

      If MRP run is implemented can we go with strategy group as 40?

      If not MRP, is there any other to implement the above scenario.

      Kindly provide us the best possible solution for the above scenario

  • Mar 11, 2017 at 05:34 PM

    Hi experts,

    Kindly provide me you inputs

    Add comment
    10|10000 characters needed characters exceeded

  • Apr 19, 2017 at 05:16 AM

    Hi experts,