How to extend Auto maintenance order generation

Hello Team

We are now using MRP for some spare parts which are assigned to GTL so that the requirements of spare parts can be run automatically.
But we have a problem that for some spare parts we have two months of planned delivery time. Now PM orders are generated only one month in advance.
So for these spare parts it might be late because material requirement would run out after PM order generation.

so how to extend the auto PM order generation from 1 month to 2 months.

Br, Kiran

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Mar 08, 2017 at 08:10 AM

    Kiran

    Change the call horizon (IP02) to ensure these orders are creted 2 months before the work is due.

    PeteA

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 08, 2017 at 09:11 AM

    Thanks Peter

    In IP02 I will have to put the maintenance plan number, is there any customizing setting to do this w/o entering plan to apply the setting to whole plant ?

    Br, Kiran

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 08, 2017 at 02:40 PM

    Hello Experts

    is there any customizing setting by we can extend the generation of auto maintenance order in system ?

    Br, Kiran

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 08, 2017 at 04:43 PM

    Kiran

    Use the mass change function in IP15: menu: Goto->Carry Out A Mass Change

    https://launchpad.support.sap.com/#/notes/2058611

    PeteA