IBP Supply / Goods Receipt processing time

Hello,

We have the following scenario:

Materials are shipped from Plant to DC to Customer;

IBP Supply currently creates an STR from Plant to DC;

We have the following need:

There is a 2 Week Goods Receipt processing time at DC; How can we model this Goods Receipt processing time at DC for that material? Material cannot be shipped out of DC to Customer until the 2 week GR processing time elapses.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    May 17 at 09:17 AM

    Hi Praveen,

    How about maintaining this in the 2 week in the leadtime parameter of the location source of supply at the DC? If transportation lead tiem is 1 week, can't you maintain leadtime attribute as 1+2 = 3 weeks?

    Please let us know if it succeeds for you.