IBP Supply / Goods Receipt processing time

Mar 07, 2017 at 10:19 PM

82

avatar image

Hello,

We have the following scenario:

Materials are shipped from Plant to DC to Customer;

IBP Supply currently creates an STR from Plant to DC and then another STR from DC to customer;

We have the following need:

There is a 2 Week Goods Receipt processing time at DC; How can we model this Goods Receipt processing time at DC for that material? So that the STR from DC to Customer reflects and accounts for this Goods Receipt processing time at DC?