IBP Supply / Goods Receipt processing time

630 Views Last edit May 04, 2018 at 02:55 AM 2 rev

Hello,

We have the following scenario:

Materials are shipped from Plant to DC to Customer;

IBP Supply currently creates an STR from Plant to DC;

We have the following need:

There is a 2 Week Goods Receipt processing time at DC; How can we model this Goods Receipt processing time at DC for that material? Material cannot be shipped out of DC to Customer until the 2 week GR processing time elapses.