cancel
Showing results for 
Search instead for 
Did you mean: 

Key figure color based on stock transfer horizon

Former Member
0 Kudos

Hi,

When we maintain SNP stock transfer horizon in SNP2 tab of product master then we can see the Distribution receipt (planned) key figure shows color for number of days/week maintained in horizon.

e.g. if We maintain stock transfer horizon as 21 days and load that product-location in planning book then distribution receipt (planned) key figure shows as color for 21 days.

Same is applicable for SNP production horizon, days maintained there shows in color in Production planned key figure.

How this get driven? I checked and there are no macros doing it.

Is there any standard setting or in built program logic?

Thanks

Yogesh

Accepted Solutions (0)

Answers (0)