Hi,

I have a scenario,

we are using variant configuration for our product where material is configured for plant A with BOM and Routing. Sales order is a cost collector and production order get created automatically based on settings made in MM. cost and revenues will be done with result analysis.

now, we have a demand from plant B which can be handled through STO. where this demand is for configurable material from plant A. Can you please answer how to handle this.

1) Demand from Plant B for configurable material in Plant A (we are creating FERT)

2) how to handle production order and costs involved in Plant A

3) here no Financial postings will happen but, cost roll up will happen at production order level (Mfg, Labor, Overhead etc.,) and sales order is a cost collector. if I use only plant A then process goes as expected (Quotation - Order - Delivery - Invoice - profitability Analysis). How to handle this with STO from Plant B ?