Hi experts!

When I create a general task list for PM (IA05) and I directly assign components without a BOM, all the components are assigned with type "L", all the fields are grayed out and I can't change the information. I couldn't find these fields in the field status configuration and I already assigned type N proposed for all the plants in customizing. Is there a way to solve this?

Thanks!

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Paul Meehan
Mar 07, 2017 at 06:54 PM
0

Hi,

It is not possible to add a non-stock component directly to the task list. The only option therefore is to do this through BOM assignment.
Note 441577 has more information.