on 07-10-2006 10:52 AM
Hi,
Is it possible to load this data source as a full update?
In June I have done it for the last month (May) and current month ( June).This had worked.
Now we have the requirement to load from the beginning of this year until July.
But no data is coming until May.
Is it problem from the datasource or perhaps the before months are already closed and now it is impossible to get data from January, February , March and April?
Thank you,
Marta.
Yes, you can load it full, but having delta enabled i should do it by delta update.
I never had problems to load historic data with this extractor, review selections in the infopackage used for load it.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Oscar,
The data is correctly extracted. On RSA3 the data is there for all months. It seems to be a problem on BW, but I could not localize it until now. On the transfer and update rules there are any kind of routines, the selection on the Infopackage is the same as on RSA3.
Thanks for your support,
Marta.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Oscar,
I reloaded the data with the right selections:
Currency type: 10
Fiscal year / period: 2006001 9999012
Controlling Area: 0010
Cost Center: 0000939000 0000939999
On the listcube still no data coming from the beginning of the year until end of May.
Still any idea?
thanks,
Marta.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
10 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.