Hello, I have a production order which is a collective order, so two orders linked for two different assemblies. Each of the assemblies have different revision levels for instance assembly one has a revision level of AB, assembly two has a revision level of AN BUT the revision level on the both orders on the collective orders is AB (from the top assembly). If I enter a single production order for assembly two is comes in with the correct revision level of AN. Is there something in configuration that controls this or something on the material master that would cause this?

10 |10000 characters needed characters left characters exceeded

Thank you, I find the tags somewhat confusing for someone who is new to this process.