No PO is created after SC is approved

Hi all,

we are implementing SRM 4.0 with CCM 2.0 in extended classic scenario. I have searched this forum for this topic but i have not found any solution.

After we have created and approved (with no-approval-workflow or 1-step-approval-workflow) a shopping cart the shopping cart stays in the status "approved" but no Purchase order or requistion is created. I hope anyone of you Pro-SRM-users knows a solution for my problem. Is it possible that the job "bbb_get_status_2" could affect this problem?

Many thanks and best regards,

Bernd

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    Jul 05, 2006 at 03:12 PM

    Hello there,

    May be the "IPC effect" =).

    Check IPC is up and running.

    If you have extended classic I am surprised you expect requisition. Do you mean requirements in the sourcing cockpit?

    Regards,

    Le Radis

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Christoph,

      you are right. Sorry, i didn't want to annoy you with needless questions.

      Many thanks for your help!

      BR,

      Bernd

  • Jul 05, 2006 at 08:08 AM

    Hello Bernd,

    Have you run the "CLEAN_REQREQ_UP" ?

    If you have run it and still have problem, please check following transaction.

    1. SM58 tRFC - network error during WF run time

    2. RZ20 - some error in backend

    3. BBP_PD - check the document status

    If you could not find the related error, please try this.

    >1. SE38 Run BBP_ALERT_SB_NOTTRANSFERED

    >2. RZ20 check the entry

    >3. Goto Web Application Monitor, re-submit

    Regards,

    Masa

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jul 06, 2006 at 04:31 AM

    Hello Bernd,

    Have you set in SRM IMG -> SRM ->SRM server -> Cross applications-> Define objects in backend sysetem->External souring= PR or PO

    It is preliminary setting, But there was no mention in the thread.

    Hence this post.

    BR

    Dinesh

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Dinesh,

      is this setting obligatory for extended classic scenario? I thought this is only necessary for classic scenario because there the documents are created in backend-system.

      BR,

      Bernd