Process chains activation after transport

11 Views

Hello guys,

we migrated all our processchains from BI 3.5 to Netweaver 2004s. Process chains were created after the transport and had to be activated manually. So far so good for development system. Now we want to transport the process chains to QS and PS. Is there a possibility to activate (but not to schedule) the process chains after the transport in Q and P systems automatically? It's lot of work to change and activate all our process chains manually in those systems. Besides, in P and Q change and activation is handled more restrictive at my client.

Kind regards,