dynamic modification rule for production order

Former Member
0 Kudos

Hi

I try to assign inspection lot for material from Production Order. I couldn't make it.

I have done in:

- MM02: assign inspection type 03,

- CA02: modify the routing of material, so after first operation is completed inspection is needed.

I put in inspection characteristics, butI couldn´t put in DMR. It isn´t active or after I press enter becomes inactive?? )

- Coois: release production order

I thought that inspection lot would be created automatically, and that material would be seen on QA32 but it wasn’t.

So I have 2 problems:

How to assign inspection to material from Production Order?

How to assign DMR to inspection characteristic from CA02?

Thank you very much for your answers

Petra

solomon_macwan
Active Contributor
0 Kudos

Hi Petra,

Another way to do it -

create a inpection plan for that material for usage 1 with the DMR.

When you create a routing, use a control key PP04 or QM01 as suggested by Craig.

Now you can assign the inspection

plan to the routing by clicking on copy Characteristics in characteristics overview in routing.

regards,

Solomon

former_member42743
Active Contributor
0 Kudos

Solomon,

That only copies in the characteritics from the inspection plan though. It doesn't actually USE the inspection plan.

In the future, if you change the inspection plan, those change are NOT reflected it the routing. It saves time by not making you enter them one by one. But you still have to make the QM settings in the routing header.

Craig

former_member42743
Active Contributor
0 Kudos

Petra,

No, you can't use the control keys you mentioned unless you change them. To use inspection characteristics in an operation and get the inspection lot for it, you must have the indicator "inspection characteristics" ticked on for the control key for that operation. If you need things like time tickets, confirmations, etc..on the same operation as the characteristics, you may need to create a new control key with the appropriate items ticked on.

Craig

PS> Somehow your question on control keys got deleted when I moved it from an answer to a comment. Please make sure you use comments and answers appropriately in the forum.

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

HI Solomon

I put DMR (H11) in field inspection characteristic, because in case that there would be many characteristics with different DMR.

regards Petra

solomon_macwan
Active Contributor
0 Kudos

Hi Petra,

You need to enter the modification rule too.

reagrds,

Solomon

Former Member
0 Kudos

Hello to all!

Solomon thank you for your reply.

I still have problems.

If I describe you what I did by steps:

in MM02 I assigned Inspection type 03

in CA02 I fullfilled in header:

and in routing I insert inspection (meritev)

and put in Inspection characteristic

Afterwards we test it. After first operation material should go to q-lot. But it didn't.

What I did wrong or what is missing?

Thanks for your help.

former_member42743
Active Contributor
0 Kudos

After first operation material should go to q-lot. But it didn't.

An 03 inspection lot is not stock relevant. No stock is ever controlled by an in-process inspection lot.

An inspection should be created, but you'll never see stock in QI or against the insp. lot.

The 04 inspection lot is stock relevant. But that typically doesn't happen until you do the GR for the material.

Craig

solomon_macwan
Active Contributor
0 Kudos

Hi Petra,

Sorry I misunderstood the question at the first time, Thank you Craig for correcting me.

You can assign the DMR at the header screen in routing. you can assign Dynamic mod. level and Modification rule.

For your reference --

Hope this will help

Regards,

Solomon

Former Member
0 Kudos

Hello to all!

Thank you for your answers.

You said that is possible also to use control key QM01.

We have these control keys:

Could you be so kind to explain me in detail (steps) how to fulfill operation for inspection inside routing?

,

Hello to all!

Thank you for your answers.

Solomon you said that is possible to use also QM01 control key. I have these options of control keys:

Could you be so kind to explain me in detail how to fullfil operation inspection inside routing?