I try to assign inspection lot for material from Production Order. I couldn't make it.

I have done in:

- MM02: assign inspection type 03,

- CA02: modify the routing of material, so after first operation is completed inspection is needed.

I put in inspection characteristics, butI couldn´t put in DMR. It isn´t active or after I press enter becomes inactive?? )

- Coois: release production order

I thought that inspection lot would be created automatically, and that material would be seen on QA32 but it wasn’t.

So I have 2 problems:

How to assign inspection to material from Production Order?

How to assign DMR to inspection characteristic from CA02?

Thank you very much for your answers

Petra

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

5 Answers

  • avatar image
    Former Member
    Mar 15, 2017 at 10:26 AM

    Hello to all!

    Thank you for your answers.

    You said that is possible also to use control key QM01.

    We have these control keys:

    Could you be so kind to explain me in detail (steps) how to fulfill operation for inspection inside routing?

    ,

    Hello to all!

    Thank you for your answers.

    Solomon you said that is possible to use also QM01 control key. I have these options of control keys:

    Could you be so kind to explain me in detail how to fullfil operation inspection inside routing?

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 15, 2017 at 11:41 AM

    Hi Petra,

    Sorry I misunderstood the question at the first time, Thank you Craig for correcting me.

    You can assign the DMR at the header screen in routing. you can assign Dynamic mod. level and Modification rule.

    For your reference --

    Hope this will help

    Regards,

    Solomon

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 17, 2017 at 06:04 AM

    Hello to all!

    Solomon thank you for your reply.

    I still have problems.

    If I describe you what I did by steps:

    in MM02 I assigned Inspection type 03

    in CA02 I fullfilled in header:

    and in routing I insert inspection (meritev)

    and put in Inspection characteristic

    Afterwards we test it. After first operation material should go to q-lot. But it didn't.

    What I did wrong or what is missing?

    Thanks for your help.

    Add comment
    10|10000 characters needed characters exceeded

    • After first operation material should go to q-lot. But it didn't.

      An 03 inspection lot is not stock relevant. No stock is ever controlled by an in-process inspection lot.

      An inspection should be created, but you'll never see stock in QI or against the insp. lot.

      The 04 inspection lot is stock relevant. But that typically doesn't happen until you do the GR for the material.

      Craig

  • Mar 17, 2017 at 07:46 AM

    Hi Petra,

    You need to enter the modification rule too.

    reagrds,

    Solomon

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 17, 2017 at 08:10 AM

    HI Solomon

    I put DMR (H11) in field inspection characteristic, because in case that there would be many characteristics with different DMR.

    regards Petra