Production Order - CO01 - where to set the Calculate Capacity reqs indicator as a default

Former Member
0 Kudos

Creating a Production Order - CO01 - on the Control Tab - field Calculate Capacity Reqs need to be set 'X' as a default. Where can this be done?

Accepted Solutions (1)

Accepted Solutions (1)

Raja_S_Reddy_B
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi
Please check the Scheduling Parameters for the respective Order Type, in the respective Plant ( in Configuration: T code : OPU3)

Please find the attached screen shot of the same


Once, maintained the above settings in the Configuration & then try to Create the Production Order with T code : CO01
kindly check & let me know your feedback/comments , for any other details/assistance required

Many thanks for the quick feedback : Best Regards : Raja Sekhara Reddy B

Answers (1)

Answers (1)

Raja_S_Reddy_B
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi
Please maintain the above settings in the Configuration & update with your feedback

Many Thanks for your feedback/comemnts
Thanks & Regards : Raja Sekhara Reddy B

Raja_S_Reddy_B
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Anthony

Would like to know your comments/feedback on the last solution proposed.
If you are still facing the problem, kindly share the details of the current status


Many Thanks for the quick & kind feedback : Best Regards : Raja Sekhara Reddy

jessica_li
Advisor
Advisor
0 Kudos

Thank you Raja. I have tested the solution, it is working.