BAdI ME_PROCESS_REQ_CUST : How to launch a custom process AFTER the LAST COMMIT

Hi experts,

I'm currently trying to figure how to launch a custom method after the LAST COMMIT, when the Purchase requisition is saved (ME52N).

In the POST method, I call a function that calls a method using a PERFORM ON COMMIT LEVEL 99.

It's too SOON, because in this method I do a SELECT on the STXH table (to get the timestamp of long texts), and I don't get the last changes I just made in the screen.

It's too SOON too if I call my method in the CLOSE method.

Any idea to resolve this the cleaniest way?

Thanks!

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Mar 03, 2017 at 08:36 AM

    Try to wrap your code in a RFC enabled FM and CALL the FM IN BACKGROUND TASK so it will be executer after the update tasks.