on 03-02-2017 12:16 PM
Hi All,
I have maintained Backward Consumption mode with Period say 15 days in MM02.
For this material I have a PIR as below,
PIR_01 requirement date - 25-02-2017 for 10 pcs
PIR_02 requirement date - 01-02-2017 for 15 Pcs
As per planning period value for upcoming sales order will consume PIR_01, since it lies within the band of Backward consumption period (15days).
My Query is, What will happen to PIR_02 which is placed outside the backward consumption period.
Thanks & Regards,
Dinesh Kumar V.
Hi Dinesh
The PIR_02, which is/are outside the backward consumption period, will remain unconsumed.
These accumulated unconsumed PIRs need to removed by executing the Reorganization run programs.
Then schedule MD74 and MD75 in Back ground using the varinats.
MD74--- Programe RM60RR20 create a Variant
MD75---Programe RM60RR30 create a Variant
Hope, this will be of some helpful info. Kindly check & let me know with your comments/feedback for any other details/assistance required
Many Thanks for your quick feedback : Best Regards : Raja Sekhara Reddy B
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Dinesh
During MRP run material will be plan But SO will not consume PIR_02.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.