Operation user Status Update through TR

We have Created '1' Operation User Status for a Status Profile ( Say A1 ) for a Particular change Request for our Client and transported to QA .Now there is another Change Request by Our Client under which we need to configure '1' more Operation User Status ( Say A2) in the same Profile. Due to some reasons Go Live of First Change Request(for Which USer Status A1 was configured) has been delayed and Client is asking for Quick Go live of Second Change Request ( For Which User Status A2 has been configured) . When I move the Customizing TR of User Status 'A2' only to Production , I am not getting sure that will it bring User Status A1 along with it or not. Can you pls suggest .

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Mar 02, 2017 at 07:40 AM

    Vivek,

    Display your TR via SE01 and navigate to the Objects tab. You should be able to see the objects in the TR and their associated values.

    You could also try importing the TR to a non-production system and test the settings first.

    PeteA