Skip to Content
0

Unable to Dispatch Planned Order to Earliest date

Mar 01, 2017 at 03:29 PM

67

avatar image

Dear Experts,

In CM25 , changed the date of planned order which is scheduled for future date to todays date and dispatched it to todays date. But system only dispatching the planned order to the originally scheduled dates and the dates also got changed to previously scheduled dates.Please advice how to schedule to current date or previous dates.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Jessica Li
Mar 11, 2017 at 05:25 PM
0

You can change the "start in past" in customizing OPU5 and try dispatching the planned order again.
best regards,
Jessica

Share
10 |10000 characters needed characters left characters exceeded
TN SAP Jun 27, 2017 at 01:09 PM
0

Thanks Jessica, But in one of the system able to dispatch it in the past date without the change in the customizing setting in OPU5.

Share
10 |10000 characters needed characters left characters exceeded