Hello ,
Thanks for your help.
CTM Run can NOT create any planned order, but Heuristic MRP can create related planned order to SO & Forecast demand qty.
Suspect issue: for the CTM LOG, why “0 Calendar” is read? But not sure.
There is 1 operation which resource = WPM_WC_01_1000_001
In RRP3, Heuristic MRP can generate Planned-order without any error.
CTM Settings:
Although there are some product is wrong, but have setted “Ignore Miss location product ” in CTM Profile.
For below log, there is NOT deleteany unform planned order, also not create any new planned order.
I manauly delete the planned order in RRP3, re-run CTM, also can NOT create any new planned order to fulfill demand of SO & forcast.
Order Selection +++ Start: 2017.03.0220:03:49
Fixed pegging between order 0000037525 and order 00mfNg317kQ} was deleted
Fixed pegging between order 0000037527 and order 00mfNg317kQ} was deleted
Fixed pegging between order 0000037530 and order 00mfNg317kQ} was deleted
Fixed pegging between order 0000037526 and order 00mfNg317kQ} was deleted
Fixed pegging between order 0000037528 and order 00mfNg317kQ} was deleted
Fixed pegging between order 0000037531 and order 00mfNg317kQ} was deleted
Fixed pegging between order 0000037534 and order 00mfNg317kQ} was deleted
Fixed pegging between order 0000037535 and order 00mfNg317kQ} was deleted
Fixed pegging between order 0000037536 and order 00mfNg317kQ} was deleted
Fixed pegging between order 0000037537 and order 00mfNg317kQ} was deleted
Fixed pegging between order 0000037538 and order 00mfNg317kQ} was deleted
Fixed pegging between order 0000037539 and order 00mfNg317kQ} was deleted
Fixed pegging between order 0000037541 and order 00mfNg317kQ} was deleted
Fixed pegging between order 0010015107 and order 0000037537 was deleted
Fixed pegging between order 0010015108 and order 0000037536 was deleted
Fixed pegging between order 0010015109 and order 0000037538 was deleted
Fixed pegging between order 0010015110 and order 0000037539 was deleted
Fixed pegging between order Stock on Han and order 0000037541 was deleted
Order Selection +++ End:2017.03.0220:03:49
Demand Prioritization +++ Start: 2017.03.0220:03:49
Demand Aggregation +++ Start: 2017.03.0220:03:49
Demand Aggregation +++ End:2017.03.0220:03:49
==> 72 Demands Determined
Demand Prioritization +++ End:2017.03.0220:03:49
Supply Categorization +++ Start: 2017.03.0220:03:49
Supply Aggregation +++ Start: 2017.03.0220:03:49
Supply Aggregation +++ End:2017.03.0220:03:49
==> 28 Supplies Determined
Supply Categorization +++ End:2017.03.0220:03:49
CTM engine version: 12.0_REL SP00, falcmake, Feb9 2017 01:51:41, Uni
Data has been reset
Read locations +++ Start: 2017.03.0220:03:50
==> 1 location(s) read
Read locations +++ End:2017.03.0220:03:50
Read sources for in-house production and products +++ Start: 2017.03.0220:03:51
==> 25 Product/Location Combinations Read
==> 4 sources of supply read (in-house production)
Read sources for in-house production and products +++ End:2017.03.0220:03:51
Read sources for external procurement +++ Start: 2017.03.0220:03:51
==> 1 sources of supply read (external procurement
Read sources for external procurement +++ End:2017.03.0220:03:51
Read resources +++ Start: 2017.03.0220:03:51
==> 1 Resources Read
==> Available capacity read for 1 time-continuous resources
Read resources +++ End: 2017.03.0220:03:51
Read calendar +++ Start: 2017.03.0220:03:51
==> 0 calendar(s) read
Read calendar +++ End:2017.03.0220:03:51
Model data uploaded
Planning version data was uploaded
Convert CTM data +++ Start: 2017.03.0220:03:52
CTM Results -> liveCache +++ Start: 2017.03.0220:03:52
==> 18 Pegging lane created
CTM Results -> liveCache +++ End:2017.03.0220:03:52
==> 17 demands were fulfilled completely and on time
==> 0 demands were fulfilled completely, but late
==> 0 demands only partially fulfilled, but on time
==> 0 demands only partially fulfilled, and late
==> 55 demands not fulfilled
Planning run completed
Result indicators for CTM planning run
Thanksfor your help.
Allen