Skip to Content

WBS budget maintain - CJ30

Hi,

When we maintain the WBS Budget through CJ30 tcode...then system is showing a document created after Save the budget.

My query is that if we maintain the wrong budget value and save it..after that maintain the Budget again through CJ30...

Then we have to delete the document created for earlier budget maintained???

Please help.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Mar 03, 2017 at 11:09 AM

    Hi Anil,

    Since SAP keep track of all the changes, we can not delete any budget posting document. However while correcting / changing the same we can give a comment in the document functionality.

    Regards,

    Punith.