Hi,

When we maintain the WBS Budget through CJ30 tcode...then system is showing a document created after Save the budget.

My query is that if we maintain the wrong budget value and save it..after that maintain the Budget again through CJ30...

Then we have to delete the document created for earlier budget maintained???

Please help.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Punith Reddy Manyam Mar 03, 2017 at 11:09 AM
0

Hi Anil,

Since SAP keep track of all the changes, we can not delete any budget posting document. However while correcting / changing the same we can give a comment in the document functionality.

Regards,

Punith.