Hi,
I have an issue to simulate and display the R/3 budget in the SRM shopping cart for a wbs element.
Classic scenario
SRM server 5.0 SP8
ECC 5.0
1- I have the bbp_budget authorization in the user profile.
2- budget badi is deactivated
3- R/3 wbs element is allocated to a budget
4- availability control is activated for that budget
5- I can create a PR in R/3 and budget availability is working fine.
6- message is issued in SRM (but wrong !) but no budget display at all ("No Budget Information Exists ")
I didn't find any relative oss note that would make me think it is a bug...
So i guess i am missing a configuration step in SRM ???
Kind regards,
Yann
Message was edited by: Yann Bouillut