Skip to Content

Map to Procurement Catalog

Hi!

After upload a CSV file from Supplier Catalog with content modifications, we don't have problem to view that the modifications are replicated in Master Catalog, however some modifications don't reach to Procurement Catalog, so we must to force the mapping between Master Catalog and Procurement Catalog.

We think that mapping has to work good from Supplier Catalog to Procurement Catalog passing through Master Catalog.

Anyone know how to resolve this?.

Our installation:

SRM_SERVER 500 0007 SAPKIBKS07

CCM 200_640 0003 SAPK-26403INCCM

Thanks a lot.

Alfonso.

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jun 16, 2006 at 09:55 AM

    Hi Alfonso,

    One more reason for yr desired update not happening in procurement catalog may be:

    Flagging 'Required' field in the respective procurement caralog ->schema->catalog characteristics->characteristics definition ->characteristics attributes.

    If this is set and the procurement catalog published then it will not allow the changes from master catalog to come in for that particular characteristic. e.g. price.

    also,

    have you gone for manual characteristic assignment instead of 'automatic charastristic assignment'?

    BR

    Dinesh

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 15, 2006 at 11:39 AM

    Hi Alfonso

    While running the program BBP_CCM_TRANSFER_CATALOG the

    Force Intial transport should be click only once at the begining of the Intial Upload and after the intial upload all delta down load tick should not be on,.

    secondly all changes from SRM to procutement catalog are automatically taken care off if they are mapped properly.

    while mapping the procurement catalog to master catalog do following steps -

    1 Go to pocurement catalog and click on the mapping option

    2 select the product categories in Master catalog and in procument catalog with same decsiption.

    3 below tick "with automatic charatertitics Assignment

    4 click on Assign catgory button indicating that the PC of master catalog is assigned to Pc of Procutrement catalog

    5 save and after saving click on the map content button so that all items in the master catalog are mapped to procurement catalog Procduct categories.

    There after all changes to SRM catalog are automatically carried on to master catalog and the same moved to respective procurement catalogs.

    regards,

    Nimish Sheth

    Do rewards points for helpful answers.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.