Can we maintain holiday for particular work center in Plant

Mar 01, 2017 at 06:53 AM

60

avatar image

Hello Team

Is there any possibilities in R/3 that we can maintain holiday to particular work center in plant ?

Br, Kiran

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Solomon Macwan Mar 01, 2017 at 08:52 AM
0

Hi Kiran,

Create a Factory calendar and assign it into Capacity header tab in work center.

regards,

Solomon

Show 3 Share
10 |10000 characters needed characters left characters exceeded

Hello Solomon

Thanks for the quick feedback, vice versa if there Is holiday in plant and we wants to run that work center then can it be possible ?

Br, Kiran

0
Former Member
Kiran Unde

You can do it - but be aware that this can have side effects if the plant runs with another factory calendar in terms of expected GR date, material availability and for your inbound and outbound shipping.

I suggest that you do proper testing of the solution.

0

Hello Experts

If there Is holiday in plant and we wants to run that particular work center then can it be possible ?

need your valuable guidance.

Br, Kiran