Can we maintain holiday for particular work center in Plant

Hello Team

Is there any possibilities in R/3 that we can maintain holiday to particular work center in plant ?

Br, Kiran

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Mar 01, 2017 at 08:52 AM

    Hi Kiran,

    Create a Factory calendar and assign it into Capacity header tab in work center.

    regards,

    Solomon