on 03-01-2017 6:53 AM
Hello Team
Is there any possibilities in R/3 that we can maintain holiday to particular work center in plant ?
Br, Kiran
Hi Kiran,
Create a Factory calendar and assign it into Capacity header tab in work center.
regards,
Solomon