Skip to Content

Planning calendar at material level

Hi Guru's

I need to stop the planning for the month of august 2017 for few materials, Because the vendor is closed during the month of august.For this i configured MD25 but not sure what periods to take. to stop the planning during the month.Please advice this is at material level in ECC

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Mar 11, 2017 at 05:33 PM

    Hi

    This is based on the calculation rule and calculation start date in the planned calendar.

    best regards,

    Jessica

    Add comment