Storage process for returns from production (internal movement) using RF

Dear colleagues,

I've set up a storage process for return products from a non-HU managed PSA to the warehouse (HU managed) using the Clear PSA functionality in EWM-Advanced Production Integration.

The storage process has the steps pick, pack and putaway for internal movements with the additional customizing (WPT, WC, SType,queues, etc). I can create a WT using the Clear PSA functionality (in NWBC), this WT assigns the correct storage process and the belonging first step (external step OB01 pick).

However, when I try to process this WT with the RF where I expect to pick the products, I receive the following screen:

/SCWM/RFUI > Manual Selection > By WO > fill in WO > then:

Program: SAPLZSCWM_RFUIZ7 - Screen number: 28

In the screen I can choose a PMAT and create a HU using the radio button F2, but that's pretty much it. Once I create a HU or if I press [enter], it will not jump to another screen.

In other words, is it possible to pick non-hu managed products to a packing station for internal movements? Or is it required to have a HU when using a storage process?

Many thanks in advance !!

Kind regards,

Zain

rf-screen.jpg (8.1 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Mar 02, 2017 at 11:30 AM

    Solved:

    Radio button is missing on the screen due to size of screen, after changing the presentation profile you will be able to see the remaining two radio buttons and further process the WO.