How to set FIORI mobile app for custom PR workflow

Hi all

PR Approval workflow is running in ECC. We want to setup FIORI Mobile app for approvers. I have done the FIORI configuration using embedded deployment method.

And now I want to build FIORI Mobile app for custom workflow. Please suggest how to go from here. What other front end and back end components I have to install and which is the correct software component. We are on 740 SP15.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

8 Answers

  • Mar 01, 2017 at 02:25 PM

    Hi Srini,

    Fiori Approve Requisitions runs on mobile browser without any development.

    https://fioriappslibrary.hana.ondemand.com/sap/fix/externalViewer/#/detail/Apps('F0401')/W13

    Regards,

    Masa / SAP Technology RIG

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 10 at 08:11 AM

    Hi Masa,

    I have gone through the link you sent.

    I have not installed FIORI ERP APPLICATIONS X1 1.0 which I will be doing with Basis help.

    After that I will Install UIX01EAP 100 - SP 0010.

    For the Backend Component: we are on SAP_APPL 617, but the link say Component Version as SAP_APPL 618. So should I Install SAP_APPL 618 and then GBAPP002 600 - SP 0012, please suggest. I am a developer, but have to take care of Basis, because we don't have a dedicated Basis support.

    I am working on Launchpad Designer Configuration as I have fewer issues and checking it.

    Also the Custom PR workflow is running, so how should I map to make it Fiori Mobile App. Please suggest fewer more details about it.

    Thank You

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 10 at 08:12 AM

    Hi Masa,
    I have gone through the link you sent,

    I have not installed FIORI ERP APPLICATIONS X1 1.0 which I will do it with Basis support and then will install UIX01EAP 100 - SP 0010 .

    For Backend, we are on SAP_APPL 617 and the links says SAP_APPL 618 - SP 0003. So should I install SAP_APPL 618 - SP 0003 and the n GBAPP002 600 - SP 0012. Please suggest as I am developer and have to take care of Basis as we don't have dedicated Basis Support.

    I am working on Launchpad Designer Issues I have after fiori configuration.

    I have also gone through the Technical Configuration and Odata Services from the link. So I have to do the corresponding Launchpad Customization in LPD_CUST correct.

    The Custom PR Approval Workflow is running in ECC, so can you please elaborate and give fewer more details on how to map the existing ECC custom workflow to run on Fiori Mobile App. Your help is highly appreciated.

    Thank You

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 01, 2017 at 04:32 PM

    Hi Masa,
    I have gone through the link you sent,

    I have not installed FIORI ERP APPLICATIONS X1 1.0 which I will do it with Basis support and then will install UIX01EAP 100 - SP 0010 .

    For Backend, we are on SAP_APPL 617 and the links says SAP_APPL 618 - SP 0003. So should I install SAP_APPL 618 - SP 0003 and the n GBAPP002 600 - SP 0012. Please suggest as I am developer and have to take care of Basis as we don't have dedicated Basis Support.

    I am working on Launchpad Designer Issues I have after fiori configuration.

    I have also gone through the Technical Configuration and Odata Services from the link. So I have to do the corresponding Launchpad Customization in LPD_CUST correct.

    The Custom PR Approval Workflow is running in ECC, so can you please elaborate and give fewer more details on how to map the existing ECC custom workflow to run on Fiori Mobile App. Your help is highly appreciated.

    Thank You

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 02, 2017 at 06:23 AM

    Hi Srini,

    Please go through wiki and configure your custom workflow by following steps mention in Chapter 7 and 8.

    Regards,

    Rehan Sayed

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 02, 2017 at 06:23 AM

    Hi Srini,

    Please go through wiki and configure your custom workflow by following steps mention in Chapter 7 and 8.

    Regards,

    Rehan Sayed

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 02, 2017 at 06:23 AM

    Hi Srini,

    Please go through wiki and configure your custom workflow by following steps mention in Chapter 7 and 8.

    Regards,

    Rehan Sayed

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 02, 2017 at 08:55 AM

    Hi Srini,

    Take a look at How to adjust custom workflow templates for SAP Fiori.

    Regards,

    Masa / SAP Technology RIG

    Add comment