Why does Sop to Demand managment doesn't transfer back dated records

Former Member
0 Kudos

Hi PP Gurus,

There are two programs RMCA9036 and RMCA9056.. these are Eq to MC74 and MC90... but both program doesn't create Planned Independent Requirement even if back dated data exists in S903 or S905 records.

It only create system date onwards Records... Is there a way to create these records in PBIM and PBED table

Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

Depends on how you made planning type, extend the time period in Planning type past to future. Example if you want record to be create from January 1st 2016 to future March 1st 2017 adding current week as open. Let us know how you made your planning type