Change of start cycle date - orders already issued?

Feb 28, 2017 at 09:32 PM

88

avatar image

Dear all,

I have a question concerning SAP PM. I need to change the start date of some cycles, in order to be closer to the yearly plan of the company. Some of the plans though have already issued the work orders for the year 2017 and 2018 - thus with the old dates.

What is the best way to identify all these orders related to the old cycles dates and delete them from the system?

I hope the question is clear.

Thank you,

Martina

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Peter Atkin Mar 01, 2017 at 07:47 AM
0

Martina

Find the maintenance plan numbers, then go to IW39 and enter these paln numbers on the selection-screen. Remove the dates from the selection-screen and tick all the checkboxes at the top of the screen, then execute the report.

Go into each order and ensure that they a closed (CLSD).

Then go back to the maintenance plans and reschdule (IP10).

PeteA