Hi,
In SAP S/4HANA Public cloud version 2308, I am setting up ETO production with Variant Configuration by following scope item 4R8 (with the dependencies from 22T). I have done the set up as recommended with multi level BoM. When I create a sales order and Switch to ETO scenario,
1. There is an Incompletion log appearing at the line item level for "Configuration", even though the configurations are intact.

2. Fiori app "Order Engineering Worklist (F4770) app is not listed even though the user is assigned with the role "BR_BOM_ENG_CUST_ORDER". If I use the other related app "Manage Order BoM", the above sales order is not appearing in the list.
3. Following is the configuration profile that I have set up for ETO.

Questions:
1. Is there any other scope Item that I need to enable for ETO with Variant configuration to work ? I have already enabled 4R8 and 22T?
2. Is there any suggestion to analyse further on the "Incompletion Log" issue for "Configuration" as I am unable find the defined Incompletion log set up for Variant configuration?
Thank you for your time
Kannan