Hi,
Now we have project progress report based on period in cne5 but we want a project progress report based on day. for example, an activity started at 2023/09/1 and will finish at 2023/09/30, when I execute cne5 report at today (2023/09/15), the plan POC is calculated for the whole period and the report shows 100% but I want the progress POC to be calculated based on "today" (50%) . Can any one help me about this?