Forecast withdraw changes

29 Views

Hi all

currently we use PGI to withdraw forecast in a fix time horizon (as my company, we set it 20 workdays btw/atw as usual), now if withdraw quantity was generated in someday, the quantity is fixed on that day, if we changed original forecast for that day, the final forecast without withdraw is incorrect. so if there are any solutions to make the withdraw mechanism become dynamic?

for example:

now we stand on 1st day morning

orginal forecast: 1st:100PCs, 2nd 100PCs,3rd 100PCs

PGI: 1st 150 PCs at 10:00 am

withdraw: 1st 100PCs, 2nd 50 PCs, 3rd 0 PC

then forecast which will join MRP should be 150 PCs for these 3 days

now on 1st day afternoon I change my forecast as

1st:150PCs,2nd:40PCs, 3rd 110 PCs

but now based on the withdraw quantity in system

then forecast which will join MRP should be 160 PCs for these 3 days

1st day: 50 PCs, 2nd day: 0 PC, 3rd day: 110 PCs

so we don't change the total forecast of these 3 days, but the forecast which will join MRP is changed.

so I would like to realize whether we can make the withdraw is relevanted by the lastest forecast? or we can say dynamic withdraw?