Dear All,
We created STO PO with quantity - 10 MT when I am create delivery against the PO then system should allow to make delivery only the PO qty ( 10 MT ) but unfortunately system allow to create delivery more than PO quantity. So, pl. suggest how can we restrict not to create delivery more than PO quantity.
& also pl. confirm can it's working for with tolerance PO.
Notes for above question :
1. In delivery item category configuration ( 0vlp ) there already assigned overdelivery option as " B - Cancel action and display error message "
2. In material master availability check there assigned " ST - Consider Only Stock " as well as we changed 01 / 02 and check also system allow to create.
3. No tolerance is maintained in PO.
Lakshmipathi Ganesan Sir, pl. suggest how can I reslove the above issue..
Thank you.
With Regards
Soumya