Hi All
I have a requirement as below.
Plant A receiving plant
Plant B issuing Plant
Order qty is 100
When there is shortage of item X in Plant A after running the MRP system should create a STO PR to plant B. Once the PR is created through MRP in Plant A its converted to STO .
Now if Plant B doesn't have stock , Run MRP in plant B its creates a normal PR which gets converted to PO and the stock is received from the vendor.
The PR created in Plant B is picking the qty as per the material master (MRP views) setting in Plant B.
I want to know what setting should be done so that MRP in plant B should consider the demand qty from Plant A i.e 100 nos. And PR created in plant B should have linkage wrt to PR Qty from plant A
Thanks in advance for your reply
Regards
Sudheer