Dear,

I have finished good material FG01 managed like MTO with strategy group 21.

In MRP, the BoM components are planned as parent material with strategy 21.

The requirement is set as 1 in MRP4 view.

Is it possible to specify another strategy group for BoM component?

I would like to adopt a custom Z1 created as strategy 21 but with another requirement type and Account Assignment Category (set as M in Z1 and not D as per standard strategy 21) and assign it to some specific BoM component.

Thank you