We use WBS with IM profile, as per OITA Tcode, it will create AUC automatically.
There are two cost centers in WBS but only one is copied to AUC.
We have checked the configuration but no misses are found but it is just not happening.
Could someone extend help to spot the issue here and fix.
Example WBS has IM assigned and the IM profile has "Manage AUC" option selected.
in WBS 123456, there are two cost centers:
Requested and Responsible:
Currently only Requested CC is copied to AUC and Resp. CC field is blank
Thanks in advance