Hi Folks,
I already checked several past questions. By the way, no one answered in a clear way.
I'd like to *create* firmed PRs within period time fence during MRP run.
KBA 2351191 seems to suggest to use MRP Type P1/2/3/4 and time fence. However, *NEW* PRs are always out of the time fence, hence *not* firmed.
This strategy firms only PRs already existing when setting time fence. I cannot say users to change time fance, run MRP, then change again time fance to firm PRs created by first MRP run.
I sure miss something. Is there any other way to firm PRs? Do I need any material master field to fulfill?
My material master contains:
MRP Type P1
Time fence: 190/200 days
Minimum lot size or rounding
Info record with delivery time
The MRP runs with:
Processing Key: NETCH
Create PRs: 1
SA Deliv. Sched. Lines: 3
Create MRP List :1
Planning mode: 3
Scheduling: 1
I saw also Jurgen answer but it didn't solved. The thing destroied me.