How to automatically firm PRs during MRP run?

87 Views

Hi Folks,

I already checked several past questions. By the way, no one answered in a clear way.

I'd like to *create* firmed PRs within period time fence during MRP run.

KBA 2351191 seems to suggest to use MRP Type P1/2/3/4 and time fence. However, *NEW* PRs are always out of the time fence, hence *not* firmed.

This strategy firms only PRs already existing when setting time fence. I cannot say users to change time fance, run MRP, then change again time fance to firm PRs created by first MRP run.

I sure miss something. Is there any other way to firm PRs? Do I need any material master field to fulfill?

My material master contains:

MRP Type P1

Time fence: 190/200 days

Minimum lot size or rounding

Info record with delivery time

The MRP runs with:

Processing Key: NETCH

Create PRs: 1

SA Deliv. Sched. Lines: 3

Create MRP List :1

Planning mode: 3

Scheduling: 1

I saw also Jurgen answer but it didn't solved. The thing destroied me.