Hi,
MRP will not place a Purchase Requisition on materials with disposition attribute V1 if the term of need > reorder point.
E.g. I created a reservation 29.8.2023 with a need date of 30.11.2023 in DBVM is marked change for the NETCH planning run.
Stock 4 pcs,
planned delivery time 30 days, Purch. 3 days = 33days.
After running MD01 with planning date 29.8.2023 no Purchase Requisition is created. In DBVM the flag is removed.
In MD03, the Purchase Requisition is also not created.
I change the planning date > 2.10.2023 I start MD01, but the Purchase Requisition is not created. Why?
If I run MD03 with planning date > 2.10.2023 the Purchase Requisition is created.
Please do you know where is the error? Or what am I doing wrong? Any idea?
As of 2.10.2023 it should be marked for MRP in DBVM but it is not. Is there any report?