For delivery type NLCC I'm trying to understand how the "scheduling button" works, which dependencies.
The STO process works fine, but when I change the delivery date I was expecting that all the other dates would be recalculated, as it happens on standard delivery processes, but for this case nothing happens.
Picking dates or loading dates are not recalculated. Even if I delete those and stay only with delivery date.. nothing happens.

I've checked the shipping points and its ok and with the corresponding dates and times needed for loading and picking. I verified the routes and also the times are there.
I've checked the default order type,

and then

Do I need to activate the DlvSchedlg?
best regards,
José Dias