Skip to Content
0
Aug 26, 2023 at 07:21 AM

BOM - Adding an Alternative Child Assembly under a Header Assembly

53 Views

Hi Experts,

The following is the Business Scenario for BOM:

- A Header Assembly A has a Child Assembly B

- For the Child Assembly B, there are two Alternate BOMs available - Alternative 1 and 2

- We need to create two Alternative BOMs for Header A, with Alternative 1 having the Child Assembly B - Alternative 1 as the Child Component, whereas the Alternative 2 should have the Child Assembly B - Alternative 2 as the Child Component.

Note that we do not require a complex solution like variant configuration.

How can the above scenario be addressed in SAP S/4HANA.

Thanks for the understanding.

Regards,

R Vijayakumar