Hello,

we have a client with the requirement to bind 2 operations together, so that they are scheduled right after each other. This is due to the fact, that the materials are set in a specific form for these 2 operations, but they are being worked on on two different work centers.

There used to be a functionality in R/3 for relationships described in this question. https://answers.sap.com/questions/10626889/scheduling-for-consecutive-process-order.html

Is there such an option in S4 Hana Public Cloud?