Hello all,
I want to do basic date scheduling for the planned order & production order.
I am selecting Scheduling type as Basic date scheduling during MRP run.
Also I have maintain Scheduling margin key(1day 1day 1day 1day) in material master.
when I run MRP & check the result, Scheduling is happened without considering the scheduling margin key.
So my question is "Does system consider Scheduling margin key during basic date scheduling or not...? "
If yes then does it have any configuration to consider Scheduling margin key during basic date scheduling?
Thanks & Regards,
Ashish Gunjal