Production order status allowing TECO with COHV (Back ground Job) for open COGI items

70 Views

Hi PP experts,

We have an issue, our client business is running with GSI_MES combination.

1. When order is created it is release automatically.

2. After that WM staging happens

3. For all components automatic back flush indicator is set.

4. Last operation has a mile stone confirmation and goods receipt done automatically.

5. The next day morning one Back ground job runs which mass processes the production orders and changing the status to TECO.

Here comes the part the client has issue with the COGI open and production orders automatically changing to TECO.

How we can achieve, so that the production orders which have open COGI items with respect to order should not allow to change the status to TECO even with the back ground Job.