Hello Experts,
My client wants to create network orders with activities and populate the activities with man hours. Also link this to WBS elements where the actual costs with be accumulated. I did some research and the indication is that I will need to implement the following
1. Activate the plan integration indicator in the CO version for the fiscal year.(SPRO)
2. Create planning profile with detail planning and unit costing information and assign to project profile(SPRO)
3. Activate plan integration in project profile (SPRO)\
Please advise if this is the only configuration required so that the budget would flow up to the WBS element. To load man hours to the activity would require that the hours be populated into a work center which would be costed at the rate set up for that activity attached to the work center.