my company has a customized program code for plan price calculations that is almost equal to the standard calculation scheme in sap. But in case of material bought jn USD it is not getting calculated correctly. The material is defined as a transfer material between German production plants, suppose A& B. The planprice in the receiving plant is calculated without initial costs from the original plant.
For eg, plan price for a transfer material in plant A should be calculated like this:
plan price in plant A = purchase price + initial costs in plant B + initial cost in plant A
but in cases where currency = USD, the initial costs from plant B is missing in above calculati