hi:everyone
i met a question that how to maintain ledtime between operation and operation,ex:i have two operations for a product,first operation need 10 min for process,second operation need 20 min,when i crete a plan order and order quatity is 1000 in PPDS,
The actual situation is that when I finish the first process 100, I start to process the second proces,This reduces the processing cycle time,i try to manitain reduction strategy of operation,but effection is not very well.
What should I do to achieve this effect?